9-30-08  Dock completed. Bottom floor textured and painted; upper floor 50% complete.  Wood floor is being acclimated to house before we lay the floor. ( First of October). Started to lay marble floors- laundry room completed. Outside of the house-all of the siding up and the core board for the stucco is up and all ready to paint.  